Manajemen Proyek
Tugas
Semua pekerjaan (WBS) lintas proyek dalam satu tempat — pantau progres, tenggat dan penanggung jawab, lalu geser kartu di Kanban untuk memperbarui status.
Tugas terbuka
114
lintas 12 proyek
Terlambat
11
perlu tindakan
Jatuh tempo 7 hari
3
hingga 26 Okt
Selesai
86
43%dari total tugas
Kelompokkan
| WBS | Tugas | Proyek | PIC | Mulai | Selesai | Progres | Status |
|---|---|---|---|---|---|---|---|
| 1.1 | Mobilisasi & direksi keetPersiapan | PRJ-2026-029Ruko Graha Niaga | MSMaya Sari | 16 Feb | 25 Feb | 100% | Selesai |
| 1.2 | Pengukuran & bowplankPersiapan | PRJ-2026-029Ruko Graha Niaga | MSMaya Sari | 21 Feb | 2 Mar | 100% | Selesai |
| 2.1 | Galian & tiang pancangStruktur Bawah | PRJ-2026-029Ruko Graha Niaga | LWLukas Wibowo | 28 Feb | 30 Mar | 100% | Selesai |
| 2.2 | Pile cap & sloofStruktur Bawah | PRJ-2026-029Ruko Graha Niaga | LWLukas Wibowo | 23 Mar | 18 Apr | 100% | Selesai |
| 3.1 | Kolom & balokStruktur Atas | PRJ-2026-029Ruko Graha Niaga | LWLukas Wibowo | 13 Apr | 26 Mei | 100% | Selesai |
| 3.2 | Pelat lantaiStruktur Atas | PRJ-2026-029Ruko Graha Niaga | LWLukas Wibowo | 2 Mei | 9 Jun | 100% | Selesai |
| 3.3 | Rangka atap bajaStruktur Atas | PRJ-2026-029Ruko Graha Niaga | LWLukas Wibowo | 30 Mei | 2 Jul | 100% | Selesai |
| 3.4 | Topping offStruktur Atas | PRJ-2026-029Ruko Graha Niaga | LWLukas Wibowo | 2 Jul | 2 Jul | 100% | Selesai |
| 4.1 | Dinding & plesterArsitektur | PRJ-2026-029Ruko Graha Niaga | LWLukas Wibowo | 9 Jun | 21 Jul | 100% | Selesai |
| 4.2 | Lantai & floor hardenerArsitektur | PRJ-2026-029Ruko Graha Niaga | LWLukas Wibowo | 7 Jul | 18 Agu | 100% | Selesai |
| 4.3 | Kusen, pintu & jendelaArsitektur | PRJ-2026-029Ruko Graha Niaga | LWLukas Wibowo | 21 Jul | 28 Agu | 100% | Selesai |
| 5.2 | Plumbing & sanitasiMEP | PRJ-2026-029Ruko Graha Niaga | LWLukas Wibowo | 2 Jul | 1 Sep | 100% | Selesai |
| 5.1 | Instalasi listrikMEP | PRJ-2026-029Ruko Graha Niaga | MSMaya Sari | 25 Jun | 4 Sep | 100% | Selesai |
| 5.3 | Fire protectionMEP | PRJ-2026-029Ruko Graha Niaga | IRIndah Rahmawati | 31 Jul | 16 Sep | 100% | Selesai |
| 4.4 | PengecatanArsitektur | PRJ-2026-029Ruko Graha Niaga | LWLukas Wibowo | 18 Agu | 20 Sep | 100% | Selesai |
| 6.1 | Testing & commissioningPenyelesaian | PRJ-2026-029Ruko Graha Niaga | TPTika Permata | 16 Sep | 2 Okt | 100% | Selesai |
| 6.2 | Punch listPenyelesaian | PRJ-2026-029Ruko Graha Niaga | MSMaya Sari | 25 Sep | 7 Okt | 100% | Selesai |
| 6.3 | BASTPenyelesaian | PRJ-2026-029Ruko Graha Niaga | TPTika Permata | 9 Okt | 9 Okt | 100% | Selesai |
| 1.1 | Mobilisasi & direksi keetPersiapan | PRJ-2026-028Gudang Cikarang | AGArief Gunawan | 2 Mar | 15 Mar | 100% | Selesai |
| 1.2 | Pengukuran & bowplankPersiapan | PRJ-2026-028Gudang Cikarang | BPBudi Prasetyo | 9 Mar | 22 Mar | 100% | Selesai |
| 2.1 | Galian & tiang pancangStruktur Bawah | PRJ-2026-028Gudang Cikarang | BPBudi Prasetyo | 19 Mar | 1 Mei | 100% | Selesai |
| 2.2 | Pile cap & sloofStruktur Bawah | PRJ-2026-028Gudang Cikarang | FAFauzan Akbar | 21 Apr | 28 Mei | 100% | Selesai |
| 3.1 | Kolom & balokStruktur Atas | PRJ-2026-028Gudang Cikarang | FAFauzan Akbar | 21 Mei | 20 Jul | 100% | Selesai |
| 3.2 | Pelat lantaiStruktur Atas | PRJ-2026-028Gudang Cikarang | BPBudi Prasetyo | 17 Jun | 9 Agu | 100% | Selesai |
| 3.3 | Rangka atap bajaStruktur Atas | PRJ-2026-028Gudang Cikarang | FAFauzan Akbar | 27 Jul | 11 Sep | 100% | Selesai |
| 3.4 | Topping offStruktur Atas | PRJ-2026-028Gudang Cikarang | BPBudi Prasetyo | 11 Sep | 11 Sep | 100% | Selesai |
| 4.1 | Dinding & plesterArsitektur | PRJ-2026-028Gudang Cikarang | BPBudi Prasetyo | 9 Agu | 8 Okt | 100% | Selesai |
| 4.2 | Lantai & floor hardenerArsitektur | PRJ-2026-028Gudang Cikarang | FAFauzan Akbar | 18 Sep | 17 Nov | 50% | Berjalan |
| 4.3 | Kusen, pintu & jendelaArsitektur | PRJ-2026-028Gudang Cikarang | BPBudi Prasetyo | 8 Okt | 30 Nov | 20% | Berjalan |
| 5.2 | Plumbing & sanitasiMEP | PRJ-2026-028Gudang Cikarang | ARAndre Rusdi | 11 Sep | 7 Des | 45% | Berjalan |
| 5.1 | Instalasi listrikMEP | PRJ-2026-028Gudang Cikarang | ARAndre Rusdi | 1 Sep | 10 Des | 50% | Berjalan |
| 5.3 | Fire protectionMEP | PRJ-2026-028Gudang Cikarang | ARAndre Rusdi | 21 Okt | 27 Des | 0% | Belum Mulai |
| 4.4 | PengecatanArsitektur | PRJ-2026-028Gudang Cikarang | FAFauzan Akbar | 17 Nov | 2 Jan | 0% | Belum Mulai |
| 6.1 | Testing & commissioningPenyelesaian | PRJ-2026-028Gudang Cikarang | TPTika Permata | 27 Des | 19 Jan | 0% | Belum Mulai |
| 6.2 | Punch listPenyelesaian | PRJ-2026-028Gudang Cikarang | AGArief Gunawan | 9 Jan | 26 Jan | 0% | Belum Mulai |
| 6.3 | BASTPenyelesaian | PRJ-2026-028Gudang Cikarang | TPTika Permata | 29 Jan | 29 Jan | 0% | Belum Mulai |
| 1.1 | Survei & pengukuran detailPersiapan | PRJ-2026-030Asuka Hotel | MSMaya Sari | 6 Apr | 18 Apr | 100% | Selesai |
| 1.2 | Kick-off meeting & RKSPersiapan | PRJ-2026-030Asuka Hotel | MSMaya Sari | 13 Apr | 21 Apr | 100% | Selesai |
| 2.1 | Konsep desain & moodboardDesain | PRJ-2026-030Asuka Hotel | NTNadia Tanjung | 16 Apr | 11 Mei | 100% | Selesai |
| 2.2 | Shop drawing & detailDesain | PRJ-2026-030Asuka Hotel | NTNadia Tanjung | 1 Mei | 31 Mei | 100% | Selesai |
| 2.3 | Approval desain klienDesain | PRJ-2026-030Asuka Hotel | NTNadia Tanjung | 31 Mei | 31 Mei | 100% | Selesai |
| 3.1 | Pengadaan HPL, veneer & hardwarePengadaan | PRJ-2026-030Asuka Hotel | SWSri Wahyuni | 21 Mei | 5 Jul | 100% | Selesai |
| 3.2 | Pengadaan kaca & aluminiumPengadaan | PRJ-2026-030Asuka Hotel | SWSri Wahyuni | 26 Mei | 20 Jul | 100% | Selesai |
| 5.1 | Mobilisasi & proteksi areaInstalasi Lapangan | PRJ-2026-030Asuka Hotel | EGEko Gunadi | 9 Agu | 16 Agu | 100% | Selesai |
| 4.1 | Rangka & kabinetProduksi Workshop | PRJ-2026-030Asuka Hotel | HKHeru Kurniawan | 20 Jun | 21 Agu | 100% | Selesai |
| 4.2 | Finishing duco / HPLProduksi Workshop | PRJ-2026-030Asuka Hotel | HKHeru Kurniawan | 27 Jul | 22 Sep | 80% | Terlambat |
| 4.3 | QC workshopProduksi Workshop | PRJ-2026-030Asuka Hotel | HKHeru Kurniawan | 7 Sep | 27 Sep | 15% | Terlambat |
| 5.2 | Plafon & partisi gypsumInstalasi Lapangan | PRJ-2026-030Asuka Hotel | EGEko Gunadi | 13 Agu | 2 Okt | 55% | Terlambat |
| 5.3 | Instalasi listrik & lampuInstalasi Lapangan | PRJ-2026-030Asuka Hotel | EGEko Gunadi | 2 Sep | 27 Okt | 15% | Berisiko |
| 5.4 | Instalasi kabinet & furniturInstalasi Lapangan | PRJ-2026-030Asuka Hotel | EGEko Gunadi | 27 Sep | 16 Nov | 0% | Belum Mulai |
| 5.5 | Finishing & touch-upInstalasi Lapangan | PRJ-2026-030Asuka Hotel | EGEko Gunadi | 6 Nov | 29 Nov | 0% | Belum Mulai |
| 6.1 | Punch list & perbaikanSerah Terima | PRJ-2026-030Asuka Hotel | TPTika Permata | 21 Nov | 6 Des | 0% | Belum Mulai |
| 6.2 | Cleaning akhirSerah Terima | PRJ-2026-030Asuka Hotel | MSMaya Sari | 1 Des | 9 Des | 0% | Belum Mulai |
| 6.3 | BASTSerah Terima | PRJ-2026-030Asuka Hotel | TPTika Permata | 11 Des | 11 Des | 0% | Belum Mulai |
| 1.1 | Survei teknis & as-builtPersiapan | PRJ-2026-037Lumina MEP | AGArief Gunawan | 11 Mei | 27 Mei | 100% | Selesai |
| 1.2 | Shop drawing MEPPersiapan | PRJ-2026-037Lumina MEP | AGArief Gunawan | 21 Mei | 25 Jun | 100% | Selesai |
| 1.3 | Approval materialPersiapan | PRJ-2026-037Lumina MEP | AGArief Gunawan | 25 Jun | 25 Jun | 100% | Selesai |
| 2.2 | Pipa, fitting & pompaPengadaan | PRJ-2026-037Lumina MEP | SWSri Wahyuni | 25 Jun | 21 Agu | 100% | Selesai |
| 2.1 | Panel LVMDP & kabelPengadaan | PRJ-2026-037Lumina MEP | SWSri Wahyuni | 18 Jun | 27 Agu | 100% | Selesai |
| 2.3 | Unit AC VRFPengadaan | PRJ-2026-037Lumina MEP | SWSri Wahyuni | 14 Jul | 16 Sep | 100% | Selesai |
| 3.1 | Cable tray & wiringInstalasi | PRJ-2026-037Lumina MEP | ARAndre Rusdi | 15 Agu | 8 Des | 50% | Berjalan |
| 3.3 | Pipa plumbing & riserInstalasi | PRJ-2026-037Lumina MEP | ARAndre Rusdi | 21 Agu | 20 Des | 40% | Berjalan |
| 3.2 | Instalasi panelInstalasi | PRJ-2026-037Lumina MEP | FAFauzan Akbar | 18 Okt | 27 Des | 0% | Belum Mulai |
| 3.4 | Ducting & ACInstalasi | PRJ-2026-037Lumina MEP | FAFauzan Akbar | 2 Okt | 28 Jan | 5% | Berjalan |
| 3.5 | Fire alarm & sprinklerInstalasi | PRJ-2026-037Lumina MEP | ARAndre Rusdi | 18 Nov | 9 Feb | 0% | Belum Mulai |
| 4.1 | Testing & commissioningTesting | PRJ-2026-037Lumina MEP | TPTika Permata | 9 Feb | 10 Mar | 0% | Belum Mulai |
| 4.2 | Training operatorTesting | PRJ-2026-037Lumina MEP | ARAndre Rusdi | 7 Mar | 20 Mar | 0% | Belum Mulai |
| 4.3 | BASTTesting | PRJ-2026-037Lumina MEP | TPTika Permata | 26 Mar | 26 Mar | 0% | Belum Mulai |
| 1.1 | Survei & pengukuran detailPersiapan | PRJ-2026-034Kitchen Pondok Indah | RKRani Kusuma | 20 Jun | 25 Jun | 100% | Selesai |
| 1.2 | Kick-off meeting & RKSPersiapan | PRJ-2026-034Kitchen Pondok Indah | BPBudi Prasetyo | 23 Jun | 26 Jun | 100% | Selesai |
| 2.1 | Konsep desain & moodboardDesain | PRJ-2026-034Kitchen Pondok Indah | NTNadia Tanjung | 24 Jun | 4 Jul | 100% | Selesai |
| 2.2 | Shop drawing & detailDesain | PRJ-2026-034Kitchen Pondok Indah | NTNadia Tanjung | 30 Jun | 12 Jul | 100% | Selesai |
| 2.3 | Approval desain klienDesain | PRJ-2026-034Kitchen Pondok Indah | NTNadia Tanjung | 12 Jul | 12 Jul | 100% | Selesai |
| 3.1 | Pengadaan HPL, veneer & hardwarePengadaan | PRJ-2026-034Kitchen Pondok Indah | HKHeru Kurniawan | 8 Jul | 27 Jul | 100% | Selesai |
| 3.2 | Pengadaan kaca & aluminiumPengadaan | PRJ-2026-034Kitchen Pondok Indah | BPBudi Prasetyo | 10 Jul | 2 Agu | 100% | Selesai |
| 5.1 | Mobilisasi & proteksi areaInstalasi Lapangan | PRJ-2026-034Kitchen Pondok Indah | BPBudi Prasetyo | 10 Agu | 13 Agu | 100% | Selesai |
| 4.1 | Rangka & kabinetProduksi Workshop | PRJ-2026-034Kitchen Pondok Indah | HKHeru Kurniawan | 21 Jul | 15 Agu | 100% | Selesai |
| 4.2 | Finishing duco / HPLProduksi Workshop | PRJ-2026-034Kitchen Pondok Indah | HKHeru Kurniawan | 5 Agu | 28 Agu | 100% | Selesai |
| 4.3 | QC workshopProduksi Workshop | PRJ-2026-034Kitchen Pondok Indah | HKHeru Kurniawan | 22 Agu | 30 Agu | 100% | Selesai |
| 5.2 | Plafon & partisi gypsumInstalasi Lapangan | PRJ-2026-034Kitchen Pondok Indah | BPBudi Prasetyo | 12 Agu | 1 Sep | 100% | Selesai |
| 5.3 | Instalasi listrik & lampuInstalasi Lapangan | PRJ-2026-034Kitchen Pondok Indah | BPBudi Prasetyo | 20 Agu | 12 Sep | 100% | Selesai |
| 5.4 | Instalasi kabinet & furniturInstalasi Lapangan | PRJ-2026-034Kitchen Pondok Indah | BPBudi Prasetyo | 30 Agu | 20 Sep | 80% | Terlambat |
| 5.5 | Finishing & touch-upInstalasi Lapangan | PRJ-2026-034Kitchen Pondok Indah | BPBudi Prasetyo | 16 Sep | 25 Sep | 0% | Terlambat |
| 6.1 | Punch list & perbaikanSerah Terima | PRJ-2026-034Kitchen Pondok Indah | TPTika Permata | 22 Sep | 28 Sep | 0% | Terlambat |
| 6.2 | Cleaning akhirSerah Terima | PRJ-2026-034Kitchen Pondok Indah | RKRani Kusuma | 26 Sep | 29 Sep | 0% | Terlambat |
| 6.3 | BASTSerah Terima | PRJ-2026-034Kitchen Pondok Indah | TPTika Permata | 30 Sep | 30 Sep | 0% | Terlambat |
| 1.1 | Survei & pengukuran detailPersiapan | PRJ-2026-031Arunika Office | RKRani Kusuma | 6 Jul | 13 Jul | 100% | Selesai |
| 1.2 | Kick-off meeting & RKSPersiapan | PRJ-2026-031Arunika Office | BPBudi Prasetyo | 10 Jul | 15 Jul | 100% | Selesai |
| 2.1 | Konsep desain & moodboardDesain | PRJ-2026-031Arunika Office | YHYoga Hidayat | 12 Jul | 26 Jul | 100% | Selesai |
| 2.2 | Shop drawing & detailDesain | PRJ-2026-031Arunika Office | NTNadia Tanjung | 20 Jul | 7 Agu | 100% | Selesai |
| 2.3 | Approval desain klienDesain | PRJ-2026-031Arunika Office | YHYoga Hidayat | 7 Agu | 7 Agu | 100% | Selesai |
| 3.1 | Pengadaan HPL, veneer & hardwarePengadaan | PRJ-2026-031Arunika Office | SWSri Wahyuni | 1 Agu | 27 Agu | 100% | Selesai |
| 3.2 | Pengadaan kaca & aluminiumPengadaan | PRJ-2026-031Arunika Office | SWSri Wahyuni | 4 Agu | 4 Sep | 100% | Selesai |
| 5.1 | Mobilisasi & proteksi areaInstalasi Lapangan | PRJ-2026-031Arunika Office | BPBudi Prasetyo | 16 Sep | 20 Sep | 100% | Selesai |
| 4.1 | Rangka & kabinetProduksi Workshop | PRJ-2026-031Arunika Office | HKHeru Kurniawan | 18 Agu | 23 Sep | 100% | Selesai |
| 4.2 | Finishing duco / HPLProduksi Workshop | PRJ-2026-031Arunika Office | HKHeru Kurniawan | 9 Sep | 12 Okt | 85% | Terlambat |
| 4.3 | QC workshopProduksi Workshop | PRJ-2026-031Arunika Office | HKHeru Kurniawan | 3 Okt | 15 Okt | 35% | Terlambat |
| 5.2 | Plafon & partisi gypsumInstalasi Lapangan | PRJ-2026-031Arunika Office | BPBudi Prasetyo | 19 Sep | 18 Okt | 65% | Terlambat |
| 5.3 | Instalasi listrik & lampuInstalasi Lapangan | PRJ-2026-031Arunika Office | BPBudi Prasetyo | 30 Sep | 1 Nov | 25% | Berisiko |
| 5.4 | Instalasi kabinet & furniturInstalasi Lapangan | PRJ-2026-031Arunika Office | BPBudi Prasetyo | 15 Okt | 13 Nov | 0% | Belum Mulai |
| 5.5 | Finishing & touch-upInstalasi Lapangan | PRJ-2026-031Arunika Office | BPBudi Prasetyo | 7 Nov | 20 Nov | 0% | Belum Mulai |
| 6.1 | Punch list & perbaikanSerah Terima | PRJ-2026-031Arunika Office | TPTika Permata | 15 Nov | 24 Nov | 0% | Belum Mulai |
| 6.2 | Cleaning akhirSerah Terima | PRJ-2026-031Arunika Office | RKRani Kusuma | 21 Nov | 26 Nov | 0% | Belum Mulai |
| 6.3 | BASTSerah Terima | PRJ-2026-031Arunika Office | TPTika Permata | 27 Nov | 27 Nov | 0% | Belum Mulai |
| 1.1 | Survei kondisi eksistingPersiapan | PRJ-2026-036Pondok Kopi House | RKRani Kusuma | 3 Agu | 10 Agu | 100% | Selesai |
| 1.2 | Perizinan RT/RW & pengelolaPersiapan | PRJ-2026-036Pondok Kopi House | BPBudi Prasetyo | 6 Agu | 14 Agu | 100% | Selesai |
| 2.1 | Bongkar plafon, lantai & sanitairBongkaran | PRJ-2026-036Pondok Kopi House | BPBudi Prasetyo | 11 Agu | 25 Agu | 100% | Selesai |
| 2.2 | Buang puing & pembersihanBongkaran | PRJ-2026-036Pondok Kopi House | BPBudi Prasetyo | 19 Agu | 28 Agu | 100% | Selesai |
| 3.1 | Perbaikan struktur & dindingStruktur & Sipil | PRJ-2026-036Pondok Kopi House | BPBudi Prasetyo | 25 Agu | 21 Sep | 100% | Selesai |
| 3.2 | Waterproofing & plesterStruktur & Sipil | PRJ-2026-036Pondok Kopi House | BPBudi Prasetyo | 13 Sep | 2 Okt | 100% | Selesai |
| 4.1 | Dipan, lemari & kitchen setProduksi Workshop | PRJ-2026-036Pondok Kopi House | HKHeru Kurniawan | 13 Sep | 27 Okt | 75% | Berjalan |
| 5.1 | Lantai granit & keramikFinishing | PRJ-2026-036Pondok Kopi House | BPBudi Prasetyo | 2 Okt | 27 Okt | 55% | Berjalan |
| 5.2 | Instalasi MEP rumahFinishing | PRJ-2026-036Pondok Kopi House | HKHeru Kurniawan | 30 Sep | 7 Nov | 45% | Berjalan |
| 4.2 | Finishing furniturProduksi Workshop | PRJ-2026-036Pondok Kopi House | HKHeru Kurniawan | 17 Okt | 10 Nov | 0% | Belum Mulai |
| 5.3 | PengecatanFinishing | PRJ-2026-036Pondok Kopi House | BPBudi Prasetyo | 4 Nov | 27 Nov | 0% | Belum Mulai |
| 5.4 | Instalasi furniturFinishing | PRJ-2026-036Pondok Kopi House | HKHeru Kurniawan | 14 Nov | 7 Des | 0% | Belum Mulai |
| 6.1 | Punch list & perbaikanSerah Terima | PRJ-2026-036Pondok Kopi House | RKRani Kusuma | 4 Des | 15 Des | 0% | Belum Mulai |
| 6.2 | BASTSerah Terima | PRJ-2026-036Pondok Kopi House | RKRani Kusuma | 18 Des | 18 Des | 0% | Belum Mulai |
| 1.1 | Survei & pengukuran detailPersiapan | PRJ-2026-038Botanica II | AGArief Gunawan | 1 Sep | 5 Sep | 100% | Selesai |
| 1.2 | Kick-off meeting & RKSPersiapan | PRJ-2026-038Botanica II | AGArief Gunawan | 3 Sep | 5 Sep | 100% | Selesai |
| 2.1 | Konsep desain & moodboardDesain | PRJ-2026-038Botanica II | YHYoga Hidayat | 4 Sep | 11 Sep | 100% | Selesai |
| 2.2 | Shop drawing & detailDesain | PRJ-2026-038Botanica II | NTNadia Tanjung | 8 Sep | 17 Sep | 100% | Selesai |
| 2.3 | Approval desain klienDesain | PRJ-2026-038Botanica II | YHYoga Hidayat | 17 Sep | 17 Sep | 100% | Selesai |
| 3.1 | Pengadaan HPL, veneer & hardwarePengadaan | PRJ-2026-038Botanica II | YHYoga Hidayat | 14 Sep | 27 Sep | 100% | Selesai |
| 3.2 | Pengadaan kaca & aluminiumPengadaan | PRJ-2026-038Botanica II | HKHeru Kurniawan | 16 Sep | 2 Okt | 100% | Selesai |
| 5.1 | Mobilisasi & proteksi areaInstalasi Lapangan | PRJ-2026-038Botanica II | FAFauzan Akbar | 8 Okt | 10 Okt | 100% | Selesai |
| 4.1 | Rangka & kabinetProduksi Workshop | PRJ-2026-038Botanica II | HKHeru Kurniawan | 23 Sep | 11 Okt | 100% | Selesai |
| 4.2 | Finishing duco / HPLProduksi Workshop | PRJ-2026-038Botanica II | HKHeru Kurniawan | 4 Okt | 21 Okt | 60% | Berisiko |
| 4.3 | QC workshopProduksi Workshop | PRJ-2026-038Botanica II | HKHeru Kurniawan | 16 Okt | 22 Okt | 0% | Belum Mulai |
| 5.2 | Plafon & partisi gypsumInstalasi Lapangan | PRJ-2026-038Botanica II | FAFauzan Akbar | 9 Okt | 24 Okt | 35% | Berisiko |
| 5.3 | Instalasi listrik & lampuInstalasi Lapangan | PRJ-2026-038Botanica II | FAFauzan Akbar | 15 Okt | 31 Okt | 0% | Belum Mulai |
| 5.4 | Instalasi kabinet & furniturInstalasi Lapangan | PRJ-2026-038Botanica II | FAFauzan Akbar | 22 Okt | 6 Nov | 0% | Belum Mulai |
| 5.5 | Finishing & touch-upInstalasi Lapangan | PRJ-2026-038Botanica II | FAFauzan Akbar | 3 Nov | 9 Nov | 0% | Belum Mulai |
| 6.1 | Punch list & perbaikanSerah Terima | PRJ-2026-038Botanica II | AGArief Gunawan | 7 Nov | 12 Nov | 0% | Belum Mulai |
| 6.2 | Cleaning akhirSerah Terima | PRJ-2026-038Botanica II | AGArief Gunawan | 10 Nov | 12 Nov | 0% | Belum Mulai |
| 6.3 | BASTSerah Terima | PRJ-2026-038Botanica II | AGArief Gunawan | 13 Nov | 13 Nov | 0% | Belum Mulai |
| 1.1 | Survei & pengukuran detailPersiapan | PRJ-2026-039Creativo Apartment | RKRani Kusuma | 14 Sep | 22 Sep | 100% | Selesai |
| 1.2 | Kick-off meeting & RKSPersiapan | PRJ-2026-039Creativo Apartment | BPBudi Prasetyo | 19 Sep | 23 Sep | 100% | Selesai |
| 2.1 | Konsep desain & moodboardDesain | PRJ-2026-039Creativo Apartment | YHYoga Hidayat | 20 Sep | 5 Okt | 100% | Selesai |
| 2.2 | Shop drawing & detailDesain | PRJ-2026-039Creativo Apartment | NTNadia Tanjung | 29 Sep | 17 Okt | 100% | Selesai |
| 2.3 | Approval desain klienDesain | PRJ-2026-039Creativo Apartment | YHYoga Hidayat | 17 Okt | 17 Okt | 100% | Selesai |
| 3.1 | Pengadaan HPL, veneer & hardwarePengadaan | PRJ-2026-039Creativo Apartment | SWSri Wahyuni | 11 Okt | 7 Nov | 35% | Berjalan |
| 3.2 | Pengadaan kaca & aluminiumPengadaan | PRJ-2026-039Creativo Apartment | SWSri Wahyuni | 14 Okt | 16 Nov | 20% | Berjalan |
| 5.1 | Mobilisasi & proteksi areaInstalasi Lapangan | PRJ-2026-039Creativo Apartment | BPBudi Prasetyo | 29 Nov | 3 Des | 0% | Belum Mulai |
| 4.1 | Rangka & kabinetProduksi Workshop | PRJ-2026-039Creativo Apartment | HKHeru Kurniawan | 29 Okt | 6 Des | 0% | Belum Mulai |
| 4.2 | Finishing duco / HPLProduksi Workshop | PRJ-2026-039Creativo Apartment | HKHeru Kurniawan | 21 Nov | 26 Des | 0% | Belum Mulai |
| 4.3 | QC workshopProduksi Workshop | PRJ-2026-039Creativo Apartment | HKHeru Kurniawan | 17 Des | 29 Des | 0% | Belum Mulai |
| 5.2 | Plafon & partisi gypsumInstalasi Lapangan | PRJ-2026-039Creativo Apartment | BPBudi Prasetyo | 2 Des | 1 Jan | 0% | Belum Mulai |
| 5.3 | Instalasi listrik & lampuInstalasi Lapangan | PRJ-2026-039Creativo Apartment | BPBudi Prasetyo | 14 Des | 16 Jan | 0% | Belum Mulai |
| 5.4 | Instalasi kabinet & furniturInstalasi Lapangan | PRJ-2026-039Creativo Apartment | BPBudi Prasetyo | 29 Des | 28 Jan | 0% | Belum Mulai |
| 5.5 | Finishing & touch-upInstalasi Lapangan | PRJ-2026-039Creativo Apartment | BPBudi Prasetyo | 22 Jan | 4 Feb | 0% | Belum Mulai |
| 6.1 | Punch list & perbaikanSerah Terima | PRJ-2026-039Creativo Apartment | RKRani Kusuma | 31 Jan | 9 Feb | 0% | Belum Mulai |
| 6.2 | Cleaning akhirSerah Terima | PRJ-2026-039Creativo Apartment | RKRani Kusuma | 6 Feb | 10 Feb | 0% | Belum Mulai |
| 6.3 | BASTSerah Terima | PRJ-2026-039Creativo Apartment | RKRani Kusuma | 12 Feb | 12 Feb | 0% | Belum Mulai |
| 1.1 | Mobilisasi & direksi keetPersiapan | PRJ-2026-040Casa Verde Clubhouse | AGArief Gunawan | 1 Okt | 9 Okt | 100% | Selesai |
| 1.2 | Pengukuran & bowplankPersiapan | PRJ-2026-040Casa Verde Clubhouse | BPBudi Prasetyo | 5 Okt | 14 Okt | 100% | Selesai |
| 2.1 | Galian & tiang pancangStruktur Bawah | PRJ-2026-040Casa Verde Clubhouse | BPBudi Prasetyo | 12 Okt | 8 Nov | 30% | Berjalan |
| 2.2 | Pile cap & sloofStruktur Bawah | PRJ-2026-040Casa Verde Clubhouse | BPBudi Prasetyo | 2 Nov | 25 Nov | 0% | Belum Mulai |
| 3.1 | Kolom & balokStruktur Atas | PRJ-2026-040Casa Verde Clubhouse | BPBudi Prasetyo | 21 Nov | 29 Des | 0% | Belum Mulai |
| 3.2 | Pelat lantaiStruktur Atas | PRJ-2026-040Casa Verde Clubhouse | BPBudi Prasetyo | 8 Des | 10 Jan | 0% | Belum Mulai |
| 3.3 | Rangka atap bajaStruktur Atas | PRJ-2026-040Casa Verde Clubhouse | BPBudi Prasetyo | 2 Jan | 31 Jan | 0% | Belum Mulai |
| 3.4 | Topping offStruktur Atas | PRJ-2026-040Casa Verde Clubhouse | BPBudi Prasetyo | 31 Jan | 31 Jan | 0% | Belum Mulai |
| 4.1 | Dinding & plesterArsitektur | PRJ-2026-040Casa Verde Clubhouse | BPBudi Prasetyo | 10 Jan | 17 Feb | 0% | Belum Mulai |
| 4.2 | Lantai & floor hardenerArsitektur | PRJ-2026-040Casa Verde Clubhouse | BPBudi Prasetyo | 5 Feb | 15 Mar | 0% | Belum Mulai |
| 4.3 | Kusen, pintu & jendelaArsitektur | PRJ-2026-040Casa Verde Clubhouse | BPBudi Prasetyo | 17 Feb | 23 Mar | 0% | Belum Mulai |
| 5.2 | Plumbing & sanitasiMEP | PRJ-2026-040Casa Verde Clubhouse | ARAndre Rusdi | 31 Jan | 27 Mar | 0% | Belum Mulai |
| 5.1 | Instalasi listrikMEP | PRJ-2026-040Casa Verde Clubhouse | ARAndre Rusdi | 25 Jan | 29 Mar | 0% | Belum Mulai |
| 5.3 | Fire protectionMEP | PRJ-2026-040Casa Verde Clubhouse | ARAndre Rusdi | 26 Feb | 9 Apr | 0% | Belum Mulai |
| 4.4 | PengecatanArsitektur | PRJ-2026-040Casa Verde Clubhouse | BPBudi Prasetyo | 15 Mar | 13 Apr | 0% | Belum Mulai |
| 6.1 | Testing & commissioningPenyelesaian | PRJ-2026-040Casa Verde Clubhouse | AGArief Gunawan | 9 Apr | 24 Apr | 0% | Belum Mulai |
| 6.2 | Punch listPenyelesaian | PRJ-2026-040Casa Verde Clubhouse | AGArief Gunawan | 17 Apr | 28 Apr | 0% | Belum Mulai |
| 6.3 | BASTPenyelesaian | PRJ-2026-040Casa Verde Clubhouse | AGArief Gunawan | 30 Apr | 30 Apr | 0% | Belum Mulai |
| 1.1 | Survei kondisi eksistingPersiapan | PRJ-2026-041Klinik Sehat Medika | AGArief Gunawan | 2 Nov | 8 Nov | 0% | Belum Mulai |
| 1.2 | Perizinan RT/RW & pengelolaPersiapan | PRJ-2026-041Klinik Sehat Medika | AGArief Gunawan | 4 Nov | 11 Nov | 0% | Belum Mulai |
| 2.1 | Bongkar plafon, lantai & sanitairBongkaran | PRJ-2026-041Klinik Sehat Medika | IRIndah Rahmawati | 9 Nov | 21 Nov | 0% | Belum Mulai |
| 2.2 | Buang puing & pembersihanBongkaran | PRJ-2026-041Klinik Sehat Medika | NTNadia Tanjung | 16 Nov | 23 Nov | 0% | Belum Mulai |
| 3.1 | Perbaikan struktur & dindingStruktur & Sipil | PRJ-2026-041Klinik Sehat Medika | NTNadia Tanjung | 21 Nov | 14 Des | 0% | Belum Mulai |
| 3.2 | Waterproofing & plesterStruktur & Sipil | PRJ-2026-041Klinik Sehat Medika | AGArief Gunawan | 7 Des | 23 Des | 0% | Belum Mulai |
| 4.1 | Dipan, lemari & kitchen setProduksi Workshop | PRJ-2026-041Klinik Sehat Medika | AGArief Gunawan | 7 Des | 13 Jan | 0% | Belum Mulai |
| 5.1 | Lantai granit & keramikFinishing | PRJ-2026-041Klinik Sehat Medika | IRIndah Rahmawati | 23 Des | 13 Jan | 0% | Belum Mulai |
| 5.2 | Instalasi MEP rumahFinishing | PRJ-2026-041Klinik Sehat Medika | NTNadia Tanjung | 21 Des | 22 Jan | 0% | Belum Mulai |
| 4.2 | Finishing furniturProduksi Workshop | PRJ-2026-041Klinik Sehat Medika | IRIndah Rahmawati | 5 Jan | 25 Jan | 0% | Belum Mulai |
| 5.3 | PengecatanFinishing | PRJ-2026-041Klinik Sehat Medika | AGArief Gunawan | 20 Jan | 9 Feb | 0% | Belum Mulai |
| 5.4 | Instalasi furniturFinishing | PRJ-2026-041Klinik Sehat Medika | IRIndah Rahmawati | 28 Jan | 17 Feb | 0% | Belum Mulai |
| 6.1 | Punch list & perbaikanSerah Terima | PRJ-2026-041Klinik Sehat Medika | AGArief Gunawan | 14 Feb | 24 Feb | 0% | Belum Mulai |
| 6.2 | BASTSerah Terima | PRJ-2026-041Klinik Sehat Medika | AGArief Gunawan | 26 Feb | 26 Feb | 0% | Belum Mulai |
| 1.1 | Survei teknis & as-builtPersiapan | PRJ-2026-042DC Bank Mitra | RKRani Kusuma | 16 Nov | 22 Nov | 0% | Belum Mulai |
| 1.2 | Shop drawing MEPPersiapan | PRJ-2026-042DC Bank Mitra | RKRani Kusuma | 19 Nov | 2 Des | 0% | Belum Mulai |
| 1.3 | Approval materialPersiapan | PRJ-2026-042DC Bank Mitra | RKRani Kusuma | 2 Des | 2 Des | 0% | Belum Mulai |
| 2.2 | Pipa, fitting & pompaPengadaan | PRJ-2026-042DC Bank Mitra | IRIndah Rahmawati | 2 Des | 23 Des | 0% | Belum Mulai |
| 2.1 | Panel LVMDP & kabelPengadaan | PRJ-2026-042DC Bank Mitra | ARAndre Rusdi | 30 Nov | 25 Des | 0% | Belum Mulai |
| 2.3 | Unit AC VRFPengadaan | PRJ-2026-042DC Bank Mitra | RKRani Kusuma | 9 Des | 1 Jan | 0% | Belum Mulai |
| 3.1 | Cable tray & wiringInstalasi | PRJ-2026-042DC Bank Mitra | ARAndre Rusdi | 21 Des | 1 Feb | 0% | Belum Mulai |
| 3.3 | Pipa plumbing & riserInstalasi | PRJ-2026-042DC Bank Mitra | ARAndre Rusdi | 23 Des | 5 Feb | 0% | Belum Mulai |
| 3.2 | Instalasi panelInstalasi | PRJ-2026-042DC Bank Mitra | ARAndre Rusdi | 13 Jan | 8 Feb | 0% | Belum Mulai |
| 3.4 | Ducting & ACInstalasi | PRJ-2026-042DC Bank Mitra | ARAndre Rusdi | 7 Jan | 19 Feb | 0% | Belum Mulai |
| 3.5 | Fire alarm & sprinklerInstalasi | PRJ-2026-042DC Bank Mitra | ARAndre Rusdi | 25 Jan | 24 Feb | 0% | Belum Mulai |
| 4.1 | Testing & commissioningTesting | PRJ-2026-042DC Bank Mitra | ARAndre Rusdi | 24 Feb | 6 Mar | 0% | Belum Mulai |
| 4.2 | Training operatorTesting | PRJ-2026-042DC Bank Mitra | ARAndre Rusdi | 5 Mar | 10 Mar | 0% | Belum Mulai |
| 4.3 | BASTTesting | PRJ-2026-042DC Bank Mitra | ARAndre Rusdi | 12 Mar | 12 Mar | 0% | Belum Mulai |